Power line expected to go into service by May 2018

from Jasper Fitzhugh

Construction to build a new power line and transmission facility to connect Jasper to the province's electricity grid is still on schedule with preliminary work expected to begin in September. ATCO Electric recently held an open house for the Jasper Interconnection Project to discuss the project's detailed impact analysis, which is available for review and comment until April 27. If approved by Parks Canada and the Alberta Utilities Commission, the company expects the bulk of the construction to take place between Oct. 1 and March 31, 2018. The transmission line is expected to go into service in May 2018. more