Gowest updates Bradshaw bulk sample work

from Canadian Mining Journal

Toronto-based Gowest Gold is now developing ore on the 45-metre level as it takes a bulk sample from its Bradshaw gold deposit at the North Timmins project, 50 kilometres northeast of Timmins. As of Oct. 17, total underground development at the Bradshaw site had reached 790 metres. The ramp was complete to the 30-metre level and the team has started to cross cut the ore there. Cross-cutting is also underway on the 45-metre level. The mine plans calls for the ramp to reach the 60-metre level, and that work will begin shortly. more