B.C. Hydro submits annual construction report for Site C to BCUC

from Energetic City

B.C. Hydro has submitted it's annual report to the British Columbia Utilities Commision about the construction of the $10.7 billion Site C Dam. The report covers construction milestones, permits and the priorities for 2018. Hydro says $2.127 billion had been spent as of Dec. 31, 2017, and that river diversion has been pushed back to 2020, a year later than planned, due to construction delays. more